Live Estimation Engine
Total Estimated Construction Cost (Material + Labor)

PKR 19,473,233

Grey Structure Total Cost

PKR 11,524,317

Finishing Total Cost

PKR 7,948,916

Category Sr Material / Detail Quantity Unit Rate Total Cost
Building Material Expenses 1 Excavation 3,105 Qu.Ft 12 37,260
Building Material Expenses 2 Bricks (First Quality) 104,052 Nos 19 1,976,988
Building Material Expenses 3 Cement 1,383 Bags 1,550 2,143,650
Building Material Expenses 4 Sand (Chenab) 5,940 Qu.Ft 60 356,400
Building Material Expenses 5 Crush (Sargodha) 2,991 Qu.Ft 178 532,398
Building Material Expenses 6 Roof Shuttering 5,978 Sft 60 358,680
Building Material Expenses 7 Steel (60 Grade) 6,180 KG 270 1,668,600
Building Material Expenses 8 PCC - Crush - Coarse Base 2,991 Qu.Ft 110 329,010
Building Material Expenses 9 Door Frames (Chughat) 16 Nos 9,000 144,000
Electric Pipe / Sewerage Pipe / Sanitary Pipe / Sui Gas Pipe 1 Electric Pipe - JOB 149,014 149,014
Electric Pipe / Sewerage Pipe / Sanitary Pipe / Sui Gas Pipe 2 Sanitary Pipe (Hot + Cold Water Lines) - JOB 223,521 223,521
Electric Pipe / Sewerage Pipe / Sanitary Pipe / Sui Gas Pipe 3 Gas Supply - JOB 111,761 111,761
Electric Pipe / Sewerage Pipe / Sanitary Pipe / Sui Gas Pipe 4 Sewerage Pipe - JOB 372,535 372,535
Electric Pipe / Sewerage Pipe / Sanitary Pipe / Sui Gas Pipe 5 Water Tank - JOB 18,000 18,000
Site Details & Preparations 1 Cleaning, Layout, Store, Motor Pump 1 Per Plot 285,000 285,000
Site Details & Preparations 2 Double Story House Drawing 1 Drawing 50,000 50,000
Site Details & Preparations 3 Plot Size (Length x Width) 1 50x90 - -
Site Details & Preparations 4 Plot Area in Sq.Ft 4500 - - -
Site Details & Preparations 5 Total Covered Area - Construction in Sq.Ft 6150 - - -
Grey Structure Labor 1 Grey Structure Labor Total - JOB 2,767,500 2,767,500
Flooring & Roof Details 1 Floor Tile 571 Sq.M 1,350 770,850
Flooring & Roof Details 2 Tile Laying Labor 6,150 Sft 50 307,500
Flooring & Roof Details 3 Roof Marble 2,700 Sft 80 216,000
Flooring & Roof Details 4 Jumbolon Sheet 2 Inch (3x6) 342 Nos 122 41,724
Flooring & Roof Details 5 Staircase Marble - JOB 75,000 150,000
Flooring & Roof Details 6 Stair Railing / Terrace (16 Gauge) 90 Ft 1,450 130,500
Bathroom Details 1 Bath Wall Tile (7 ft) 94 Sq.M 1,400 131,600
Bathroom Details 2 Tile Laying Labor 1,008 Sq.Ft 50 50,400
Bathroom Details 3 Bath Set / Commode / Basin / Mirror / Towel Rod - JOB 69,500 278,000
Bathroom Details 4 Plumber Labor - JOB 338,250 338,250
Kitchen Details 1 Wall Tile (4 ft) 20 Sq.M 1,400 28,000
Kitchen Details 2 Tile Laying Labor 216 Sq.Ft 50 10,800
Kitchen Details 3 Granite / Marble Countertop - Job 1,200 102,000
Kitchen Details 4 Kitchen Cabinet 2 Kitchen 433,027 866,053
Kitchen Details 5 Stove / Kitchen Hood / Sink Double 2 Kitchen 51,000 102,000
Electrical Material Requirement 1 Wires / Fans / Exhaust Fan - Job 866,053 866,053
Electrical Material Requirement 2 Switches, Sockets, Lights, DB, Back Box etc. - Job 259,816 259,816
Electrical Material Requirement 3 Electrician Labor - JOB 399,750 399,750
Woodwork Details 1 House Main Door (Solid) / Rooms / Bath / Kitchen - Job 1,600 404,800
Woodwork Details 2 Windows etc / Safety Grills 296 Sq.Ft 1,600 473,600
Woodwork Details 3 Safety Grills 296 Sq.Ft 300 88,800
Room Ceilings & Paint Work 1 Room Ceilings 6,150 Sq.Ft 100 615,000
Room Ceilings & Paint Work 2 Paint Work / Rockwall etc. 25,335 Sq.Ft 52 1,317,420